Home > Managing Timesheets, Expenses and Task Entries > Mass Updating Task, Time, and Expense Entries > Examples of Using Mass Update > Example—Changing the Standard Pay Rate
Example—Changing the Standard Pay Rate
Scenario: From 15-Aug-07 you want to change the Standard Pay Rate to $10 for all Research Employees of the Greenlite Help Desk project.
| |
Note: Since task elements and expense entry statuses are user-defined elements, each organization may have its own items. However, whatever you may call the items, the steps to be followed will be the same as described here. |
|
Solution: To change the Standard Pay Rate:
- Click on Mass Update… in the View Sheets tab, to open the Mass Update screen.
- In the Elements panel, click on the
button in the Project row and select Greenlite Help Desk.
- In the Phase row, click on the
button and select Research.
-
In the Employees panel, check Change rates.
When you check Change rates, the Rate, Start Date and End Date items will become visible.
- Select Standard Rate: Pay Rate Tab from the drop-down list.
- Type 10 in the Rate box.
-
Using the Date Picker, set the Start Date field to 15-Aug-07.

- Click the OK button to update the entries.
See also
|